Maintenance
06-237518-001
6-3
July 2018
6-4
MONTHLY
6-4.1
Check Kidde IGS Cylinder Pressure
Check the Kidde IGS cylinder pressure gauges for proper operating pressure (refer to
Section 1-5). If the pressure gauge indicates a pressure loss (adjusted for temperature) of
more than 5%, it shall be refilled or replaced. Remove and recharge the cylinder as instructed
in Section 7-6. Cylinders should have a pressure of either 300 bar gauge at 15°C (4351 psig
at 60°F) or 200 bar gauge at 15°C (2901 psig at 60°F) depending on the pressure
specified on the label.
6-5
EVERY 3 MONTHS
In addition to the monthly requirements, test control and detection in accordance with national
Standards and the control panel manufacturer.
6-5.1
Selector Valve Inspection
Manually open and then fully close all selector valves using the appropriate operating handle.
6-5.2
Verify Personnel Records
Check that all personnel who may have to operate the system are properly trained and
authorized to do so. All new employees must be instructed in its use.
6-5.3
Inspect Hazard Access
Ensure access to hazard areas, manual pull stations, discharge nozzles, and cylinders are
unobstructed and nothing obstructs the operation of the equipment or distribution of agent.
Содержание 400 Series
Страница 2: ...Table i Revision History Revision Change Description AA Initial Release ...
Страница 16: ...July 2018 xiv 06 237518 001 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 157: ...06 237518 001 A 1 July 2018 APPENDIX A SAFETY DATA SHEETS ...
Страница 188: ...July 2018 A 2 06 237518 001 THIS PAGE INTENTIONALLY LEFT BLANK ...
Страница 189: ......