3- 4 Keysight N5290/1A Installation Guide
System Installation
Receiving the System
3-
Receiving the System
Receiving the System
The N5290/1A system components will arrive packaged separately. For a
complete list of components shipped with your system, refer to
.
When the entire shipment has arrived, contact Keysight Technologies to
arrange for system installation. See
“Keysight Support, Services, and
Keep the shipping containers until the system checklist has been completed,
and the system has been checked for physical damage.
If the shipping container is damaged or the packaging material shows signs of
stress, notify the carrier as well as Keysight Technologies. Keep the shipping
materials for the carrier’s inspection. Keysight Technologies will arrange for
repair or replacement of damaged equipment without waiting for a claim
settlement from the carrier. Refer to
“Keysight Support, Services, and
Keysight Technologies Customer Engineering
A Keysight Technologies Customer Engineer will be assigned to help you install
the system. During installation, the Customer Engineer will do the following:
— Unpack the system components.
— Verify the system parts list, see
.
— Initialize the PNA as described in E8356-90001 Quick Start Guide that
comes with every PNA.
— Run the Operator’s Check of the PNA as described in the E8356-90001
Quick Start Guide that comes with every PNA.
— Connect the N5292A millimeter head controller to the PNA. Install the
N5293A or N5295A millimeter-wave frequency extender test head modules.
— Run the Operator’s Check of the system using the procedure in
— Run the System Verification as described in
— Provide training for one user.
The N5292A millimeter head controller and the test head modules are
sensitive to electrostatic discharge (ESD). Ground your work station before
unpacking and installing the test head modules. See
Discharge Protection” on page 1-7
.