Commissioning
Installation manual V3.28
45
© KEBA
Activate commissioning mode
To activate the charging station commissioning mode, proceed as follows:
1) Set DIP switch DSW2.8 to ON (see
2) Restart the charging station by pressing the "Service button" until the
first beep (approx. 1 second).
Commissioning mode is activated as soon as the LED bar lights up orange.
You now have approx. 10 minutes to perform the required inspections and
acceptance tests. The contactor is then deactivated and the charging station
goes into an error state. This is indicated by the LED bar (white/red/red/red).
By restarting via the "Service button", the commissioning mode can be reac-
tivated.
Information
The energy in commissioning mode is taken into account when displaying
the total energy. During the commissioning mode, the display is displayed
in "watt-hours" (Wh).
Deactivate commissioning mode
In order to be able to operate the charging station properly, the commission-
ing mode must be deactivated again. To do this, proceed as follows:
1) Set DIP switch DSW2.8 to OFF (see
2) Restart the charging station by pressing the "Service button" until the
first beep (approx. 1 second).
The charging station starts up again in normal mode and is ready for opera-
tion.
9.2
Perform safety checks
Before commissioning, check the effectiveness of the safety measure(s) of
the system according to the nationally applicable regulations.
Electrical systems or devices must be checked by the installer of the system
or device before commissioning. This also applies for the expansion or modi-
fication of existing systems or electrical devices. It is essential that all condi-
tions for the safety measures are observed.
For example, the following points are to be taken into account:
●
The checks (continuity of the connections of the protective conductor, in-
sulation resistance, RCD (FI) triggering current, triggering time, etc.) are
to be performed.
●
The measurement devices must comply with the national regulations!
●
The measurement results are to be documented. A test report is to be
created and saved before the check.