39
KaDeck
3.26
Versatile air conditioning for offices and administration buildings
Installation and operating instructions
7
Operation and commissioning
7.1 Pre-commissioning checks
Kampmann GmbH can also perform a functional
check (optional). For contact details please refer to
Chapter 1.4 "Customer Service" on page 5.
DANGER!
Check before initial commissioning whether all
necessary conditions have been met so that the unit
can function safely and properly.
IMPORTANT NOTE!
Refer to the separate instructions for operation
using the Kampmann room controller.
Structural tests:
Is the unit installed mechanically securely?
Are all accessories and the panel securely fitted?
Has the transport guard been removed from the impeller?
Electrical tests:
Is all cabling laid in accordance with the applicable
regulations?
Are all wires connected in accordance with the electric
wiring diagrams?
Is the protective conductor connected and wired
throughout?
Water-side test:
Is the flow and return pipework properly connected?
Are the valves correctly fitted? (Note the permitted
installation position of the actuators!)
Are all valves and actuators fitted correctly?
Are the shut-off valves on-site open?
Condensate drain (only with units with a cooling function):
Has the condensation drain been checked using the water
fed in for test purposes?
Clean the condensate tray before initial commissioning and
remove dirt and site dust.
Is the condensation pump alarm contact triggered before
the tray overflows?
Are all the hoses from the condensation pump fixed with
the clamps and are all bends made without kinks?
Check the operation of the condensation pump to ascertain
whether noises are produced by the hoses hitting the unit
and eliminate this by fixing the hoses in place.