Summary Checklist
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
JUNOSg 3.0 G10 CMTS Hardware Guide
82
Summary Checklist
Table 32 provides a summary checklist of the pre-installation requirements. You should
complete and review this checklist with field engineers to ensure the installation site is
prepared for installing the G10 CMTS.
Table 32: Pre-Installation Requirement Summary Checklist
Requirement
Verified
Safety
Grounding straps provided for ESD protection
Compliance verified with all local and national regulatory requirements
Equipment to be positioned in a clear, dry, dust-free area
Power
AC Power
AC-input supply operates within range of 100 to 240 VAC and 47 to 63 Hz
Appropriate circuit protection in place for compliance with area electric regulations
Separate AC-input power supply sources for CMTS A and B domains
DC Power
DC-input supply operates within range of –36 to –75 VDC
Appropriate circuit protection in place for compliance with area electric regulations
Separate DC-input power supply sources for CMTS A and B domains
Environment
Ambient temperature conditions satisfied
Ambient humidity conditions satisfied
Altitude conditions satisfied
Vibration conditions satisfied
Mounting
19-inch rack, 23-inch rack, or appropriate non-standard rack or shelf available
Cable organizer available for mounting rack
Adequate access clearance to front, rear, and sides of CMTS
Hardware
Specified tools and supplies available
Test equipment available for installation and verifying RF setup
Installation Site
Characterization of RF Plant/HFC environment parameters completed
Characterization of existing DOCSIS services completed
Characterization of upstream CMTS parameters completed
Characterization of downstream CMTS parameters completed
Содержание G10 CMTS
Страница 8: ... JUNOSg 3 0 G10 CMTS Hardware Guide viii ...
Страница 18: ... JUNOSg 3 0 G10 CMTS Hardware Guide 2 ...
Страница 34: ...G10 CMTS Hardware Overview JUNOSg 3 0 G10 CMTS Hardware Guide 18 ...
Страница 46: ...DOCSIS Module JUNOSg 3 0 G10 CMTS Hardware Guide 30 Figure 12 DOCSIS Module Front Panel HotSwap ...
Страница 55: ... Hardware Component Overview Chassis Control Module 39 Figure 15 Chassis Control Module Front Panel Eth0 ...
Страница 72: ...Chassis Rear Modules JUNOSg 3 0 G10 CMTS Hardware Guide 56 Figure 21 Hard Disk Module Rear Panel C O M Eth ...
Страница 82: ... JUNOSg 3 0 G10 CMTS Hardware Guide 66 ...
Страница 112: ...Rack Mounting JUNOSg 3 0 G10 CMTS Hardware Guide 96 Figure 25 Air Flow Through Chassis ...
Страница 116: ...Rack Mounting JUNOSg 3 0 G10 CMTS Hardware Guide 100 Figure 29 Rack Fully Populated with Three G10 CMTS Chassis ...
Страница 118: ...Install Power Supplies JUNOSg 3 0 G10 CMTS Hardware Guide 102 Figure 30 Power Supply Installation 1 2 ...
Страница 138: ...Connect to Power Sources JUNOSg 3 0 G10 CMTS Hardware Guide 122 Figure 39 DC Power Transition Module ...
Страница 148: ... JUNOSg 3 0 G10 CMTS Hardware Guide 132 ...
Страница 156: ...Upstream RF Measurement JUNOSg 3 0 G10 CMTS Hardware Guide 140 ...
Страница 188: ... JUNOSg 3 0 G10 CMTS Hardware Guide 172 ...
Страница 196: ...Radio Frequency RF Specifications JUNOSg 3 0 G10 CMTS Hardware Guide 180 ...
Страница 202: ...EIA Channel Plans JUNOSg 3 0 G10 CMTS Hardware Guide 186 ...
Страница 203: ... 187 Part 5 Index Index on page 189 ...
Страница 204: ... JUNOSg 3 0 G10 CMTS Hardware Guide 188 ...
Страница 209: ... Index 193 Index V ventilation 69 89 95 101 124 161 162 167 video servers 7 voltage power supply 27 ...
Страница 210: ... Index JUNOSg 3 0 G10 CMTS Hardware Guide 194 ...