Jabiru J450 Constructors Manual
Testing>Flight testing
Tuesday, April 6, 2010
330 of 343
Sequence #2
– First flight and rigging tests
Pre-flight
Print and use the Flight Testing form
Sequence #2
for each test flight in this sequence.
Recording
Use a kneeboard or clipboard to hold the Flight Test forms and record details of each test
flight, however the first priority must always be to
fly the aircraft
so write things down
only
when it is safe to do so.
Loading
Load the aircraft with the test pilot and 20 litres of fuel in each wing tank.
If you have followed the instructions in the
Testing>Calibrate fuel gauges
task you should
already have 20 litres per side at this point, if not then drain or add fuel as required.
Engine Start and Run-up
Start the engine normally, taxi to the run-up area and perform an engine run-up.
Check temperatures and pressures and make sure that the idle is correct when the engine is
warm – it should idle at around 900 rpm.
Pre-take off Checks
Record the date and engine hours as well as the wind direction and strength, the OAT, the
Runway in use and the Pressure Altitude. Set the altimeter back to the local QNH.
Check controls for full and free movement and correct sense – see each control surface
movement. Any sense of controls binding
must
be addressed before proceeding.
Listen for traffic and wait for the traffic to clear for first flight. Carry out the pre-takeoff
checks specified in the Owners Manual.
Advise all traffic that a first flight is to be conducted.
Содержание J450
Страница 1: ...Jabiru J450 Constructors Manual from kit serial number 659...
Страница 42: ...Jabiru J450 Constructors Manual Pre Paint Fuselage Undercarriage Fit main gear Tuesday April 6 2010 42 of 343...
Страница 95: ...Jabiru J450 Constructors Manual Pre Paint Fuselage Empennage Fit elevator Tuesday April 6 2010 95 of 343...
Страница 105: ...Jabiru J450 Constructors Manual Pre Paint Fuselage Empennage Fit rudder Tuesday April 6 2010 105 of 343...
Страница 119: ...Jabiru J450 Constructors Manual Pre Paint Fuselage Interior Console Pre fit handbrake Tuesday April 6 2010 119 of 343...
Страница 126: ...Jabiru J450 Constructors Manual Pre Paint Fuselage Interior Console Fit control stick Tuesday April 6 2010 126 of 343...
Страница 137: ...Jabiru J450 Constructors Manual Pre Paint Fuselage Interior Fuel system Tuesday April 6 2010 137 of 343...
Страница 167: ...Jabiru J450 Constructors Manual Pre Paint Wings Cut aileron cable openings Tuesday April 6 2010 167 of 343...
Страница 217: ...Jabiru J450 Constructors Manual Post Paint Fuselage Electrical wiring diagrams Tuesday April 6 2010 217 of 343...
Страница 218: ...Jabiru J450 Constructors Manual Post Paint Fuselage Electrical wiring diagrams Tuesday April 6 2010 218 of 343...
Страница 219: ...Jabiru J450 Constructors Manual Post Paint Fuselage Electrical wiring diagrams Tuesday April 6 2010 219 of 343...
Страница 220: ...Jabiru J450 Constructors Manual Post Paint Fuselage Electrical wiring diagrams Tuesday April 6 2010 220 of 343...
Страница 238: ...Jabiru J450 Constructors Manual Post Paint Fuselage Interior Fit console controls Tuesday April 6 2010 238 of 343...
Страница 240: ...Jabiru J450 Constructors Manual Post Paint Fuselage Interior Fit console controls Tuesday April 6 2010 240 of 343...