v240M – Marine Satellite Communication System
50
Hook the two frame legs using the lifting strap as shown in
j
, and tie the strap as shown in
k
in
figure 61. Once secured and lightly tensioned using a crane, check to be sure the straps match
the vertical connection lines of the Radome panels as shown in .
Figure 61. Hook and Tie Lifting Strap
Figure 62. Lifting up the Radome using the Crane Hook
Radome Mounting
Lift up the Radome hanging all four straps on a crane hook as shown in figure 62. Straighten out
the lifting straps as shown below prior to lifting the entire load of the antenna.
j
k
l
l
a
a
Содержание v240M
Страница 2: ......
Страница 4: ...INDEX...
Страница 7: ...7 Intellian v240M Introduction Intellian v240M Features System Configuration INTRODUCTION...
Страница 12: ...v240M Marine Satellite Communication System 12...
Страница 52: ...v240M Marine Satellite Communication System 52...
Страница 66: ...v240M Marine Satellite Communication System 66...
Страница 124: ...v240M Marine Satellite Communication System 124 Figure 106 Satellite View Tab for s80HD and t240CK...