Installation Manual
iSiteC BTS3601C CDMA Base Station
Hardware Installation
3
Installing RF Antenna and Feeder System
3-27
Figure 3-35
Feeder upper end fixed on tower
2
(1)
(2)
(2)
(1) 1-for-1 fixing clip
(2) 1-for-3 fixing clip
Figure 3-36
Feeder fixing clip
5)
Connect the jumper between antenna and feeder and perform waterproof and
encapsulation treatment to the connectors. Attach a temporary label at the point
10cm away from the jumper end.
3.7.3 Routing Feeder
Routing procedure:
1)
Design the feeder arrangement according to the sector requirement in the
engineering design. Determine the arrangement and lead-in plan. Usually, there is
one row or column of feeders in a sector arranged in the same sequence.
2)
Route the feeders according to the planned sequence.
3)
Arrange the feeders neatly while fixing them onto the tower or the cabling rack with
fixing clips. Meanwhile, mount the feeder grounding clip and attach feeder labels.