ECC500
User Manual
4 Installation and Commissioning
Issue 05 (2020-03-16)
Copyright © Huawei Technologies Co., Ltd.
27
4
Installation and Commissioning
4.1 Installation and Commissioning Flowchart
shows the flowchart for installing and commissioning the ECC500.
Figure 4-1
ECC500 installation and commissioning flowchart
4.2 Installing Devices
4.2.1 Installing a Rack-mounted ECC500
Prerequisites
The installation position has been determined.
The following tools are available: Phillips screwdriver, flat-head screwdriver, and rubber
mallet.
Context
A flat-head screwdriver can be used as a floating nut mounting bar.