4.6.2.2 Cascades
As a basic principle, the TopTronic
®
should perform cas-
cade control. This ensures an environmentally and prod-
uct-friendly method of operation. However, if an external
cascading strategy is planned and boiler performance
control is carried out, frequent cycles should be avoided
(at least 12 minute burner run time).
Please observe the notes in the engineering
documents of the responsible Hoval sales
company with respect to the appropriate hy-
draulic switching!
4.7
Sound insulation
The following measures are possible for sound insulation:
• If living areas are above or below the boiler room, make
the boiler room walls, ceiling and floor as solid as possible.
•
Connect pipes flexibly using expansion joints.
• Connect circulating pumps to the piping network using
expansion joints.