5 Pre-Installation Checklist
GE Healthcare Site Readiness Checklist
GEHC Global Order # :
Customer:
GEHC On-site Representative :
MI Supplier:
Name of customer reviewed with :
Lead Installer:
GEHC PMI :
Phone Number:
Target Site Prep Completion Date:
Helper:
The customer is responsible for proper site preparation and site readiness regardless of any GEHC inspections/assessments.
For MR Magnet Delivery: Ensure cryogen vents, power for the cooling system and exhaust fan system are installed and operational (0.7T, 1.5T
& 3T) and chilled water supply is available 24x7 that meets system cooling equipment requirements.
Inspection Date:
Item #
GEHC Minimum Requirements
Storage:
Is item
ready?
Predict (Pre-ship) Verify (Deliv‐
ery):
Is item
ready?
Validate
(Mech In‐
stall):
Is item
ready?
Comments
If "N", please enter in com‐
ments or action plan
Is this
item
ready?
Will
item be
ready?
1
Equipment installation drawings must
match actual room size and must meet
clearance requirements. Deviations that
meet installation requirements may be
red-lined, if red-lining is allowed by local
code. Seismic requirements are identified
on construction drawings.
X
2
Delivery route to installation or storage
area meets requirements and has been
discussed and scheduled with the custom‐
er. Ensure floor protection is discussed,
requirements identified, and will be avail‐
able at time of delivery and installation.
X
3
Rooms that will contain equipment, includ‐
ing storage areas, are dust free. Room
security to prevent unauthorized access
and theft has been discussed with cus‐
tomer. The customer is aware of these
security issues, implications and respon‐
sibility.
4
In room HVAC ductwork and units (in
room) must be mechanically installed and
dust free. Installation rooms appear to
meet environmental conditions (see Fur‐
ther Definitions) and observed issues
have been communicated to the custom‐
er. If being stored, storage area must meet
PIM storage criteria.
5
Ceiling grid is installed, Unistrut is located
per the installation drawings, and perma‐
nent lighting is installed and operational.
X
6
Floor is clean and prepared for final floor
covering. Customer has verified floor lev‐
eling meets the equipment installation
drawings and PIM specs and no visible
defects are observed. Gantry and table
baseplate are installed prior to delivery (if
applicable)
X
Innova 2121-IQ/3131-IQ Biplane Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare
Direction 5177951-4-1EN, Revision 1
202
5 Pre-Installation Checklist