MA-005 - MINITRANS Installation Manual - Rev 3.1
29-Sep-15
Page 14 of 85
The chosen location should take account of the potential requirement for
testing an onsite water deluge system (if applicable), such that the product is
not located in the direct line of water jets. While the product provides IP55-level
water spray protection, a water deluge system could exceed IP55 thresholds
depending on the location, pressure and direction of the water jets. See the
MINITRANS User Guide for further recommendations around testing a water
deluge system.
7.1
Mounting Stand Installation
It is important that the product be installed in a secure manner. For this reason, GE offers
an optional mounting stand. If the GE-manufactured mounting stand has not been
purchased, a stand must be constructed as outlined in Section 7. If the mounting stand is
purchased with the product, the product is supplied attached to a top stand and slotted
between the legs of the bottom stand for additional protection and ease of handling.
The GE-manufactured mounting stand shall be secured to the mounting surface as
follows:
The mounting stand shall be placed upright on a suitable mounting surface e.g. a
flat concrete pad (see Section 7 for details).
Use the mounting stand (recommended) or the dimensions from the mounting
stand footprint drawing (see Appendix G) to mark at least one hole for each of the
four mounting tab points.
Use M8 threaded fasteners with a recommended minimum length of 80 mm for the
concrete pad (or other suitable concrete anchors) to secure the mounting stand to
the mounting surface.
Ensure that the stand is within 5 degrees of level and plumb. If necessary, use shims
under the mounting stand feet to level the stand.
See Appendix F for a drawing of the stand with the product mounted.