Fusion Installation & Commissioning Manual Approved document No UI-FBU-01 issue 3.0
13
Knockouts should be removed with
a sharp tap at the rim of the knock-
out using a flat 6mm broad-bladed
screwdriver. Use of excessive force
will damage the enclosure around
the knockout.
INSTALLATION (Continued)
Planning the cable layout in the panel
The detector and sounder circuit cabling is classed as extra low voltage and must be segregated
away from mains voltages.
NOTE. The Main PCB should be removed before any knockouts.
Always ensure that if a knockout is removed, the hole is filled with a good quality cable gland. Any
unused knockouts must be securely blanked off.
Содержание FBUL NP12-12
Страница 2: ......
Страница 27: ...Fusion Installation Commissioning Manual Approved document No UI FBU 01 issue 3 0 27 LOOP PCB PCFSB11 Loop Card...
Страница 35: ...Fusion Installation Commissioning Manual Approved document No UI FBU 01 issue 3 0 35...
Страница 45: ...Fusion Installation Commissioning Manual Approved document No UI FBU 01 issue 3 0 45...
Страница 87: ......
Страница 88: ......