Construction Hoist Fraco SEH Premium Range
Assembly and Operating Manual
Page 31 of 69
doc no. 98030718-01
7.3 Extending
the
mast sections and mast tie to the building
If the equipment is erected in front of scaffolding it must be anchored to the building.
NOTE
It may also be anchored directly to the scaffolding if the scaffolding has been designed for the
additional load (see mast tie forces).
7.3.1 Assembling the mast sections up to approx. 30 ft (9 m) high
ATTENTION
Vertically align mast sections from the start using a spirit level. This must also be checked
when attaching each mast bracket.
The following points must be observed:
-
the installers ascend in the car; operation is from the car control
-
The load capacity during assembly is max. 3300 lbs (1500 kg)
The equipment is assembled from the car, with swing stage and/or scaffolding (if there is
any).
To start with the car on the ground:
Depending on the model, open the sliding gate or base enclosure door.
Open the car's sliding gate.
Load the car with mast sections, parts for mast tie and tools
(max. 3300 lbs (1500 kg))
.
Close the door of the base enclosure.
Close the sliding door of the car from the inside.
Use the ladder to climb up on to the roof.
Plug in the installation remote control (1) into the power panel AS2 (2)
Now the hoist can be operated from the roof top.
Turn the "service" key switch (3) to on position.
Fig. 21 Installation remote control
Fig. 22 Power panel AS2
1
2
3