CONSTRUCTION OF FRAMEWORK AND WORK
PROCEDURE
The structure should be completed from start to finish in the following order
1.
Base preparation
2.
Construction of frame assemblies
3.
Joining of sub-assemblies to make full size frame
4.
Securing structure to the base and wall
5.
Glazing
6.
Finishing off
Each of the above procedures are detailed at the appropriate stages of this booklet.
BASE SIZE AND PREPARATION
(for brick/concrete bases only)
Kensington
6’ model
Length
(Dimension B)
Width
(Dimension A)
√
Square
External ridge
height
6 x 6 model
1.960m
1.915m
2.7402m
2.387m
8 x 6 model
2.578m
1.915m
3.2114m
2.387m
10 x 6 model
3.196m
1.915m
3.7258m
2.387m
12 x 6 model
3.814m
1.915m
4.2678m
2.387m
14 x 6 model
4.432m
1.915m
4.828m
2.387m
16 x 6 model
5.050m
1.915m
5.401m
2.387m
18 x 6 model
5.668m
1.915m
5.983m
2.387m
20 x 6 model
6.286m
1.915m
6.571m
2.387m
CONSTRUCTION OF THE FRAMEWORK ASSEMBLIES
The building is divided into a number of different frame assemblies.
1.
Right hand gable end frame
2.
Shelf installation
3.
Left hand gable end frame
4.
Front frame assembly
5.
Roof frame assembly
6.
Double door assembly
7.
Roof vent assembly
8.
General assembly of greenhouse unit.
9.
Construction and installation of louvre
NB
. If you have a corner location, i.e. one end missing (R-type)– all base lengths reduced by
40mm.
All bases of any material must be level and square and built to exact outside measurements.
Содержание KENSINGTON 10 x 6
Страница 1: ......
Страница 2: ......
Страница 3: ......
Страница 17: ...DOOR FRAME...
Страница 36: ...6 WIDE LT TOUGHENED GLASS PLAN Glass pane for standard door on gable end Louvre on rear end...
Страница 39: ...OPTIONAL EXTRAS RAIN WATER KIT FOR GUTTERING...
Страница 40: ...ELITE 1407...