9.1 Switching on the Green Motion Building EV charger
Before switching on the unit, please perform the checks below:
Step 1 .
Check that the equipment is correctly fixed to the wall or to the floor in accordance with local regulations.
Step 2 .
Check that the AC grid connections have been made correctly in accordance with local regulations.
Step 3 .
Perform checks on the continuity of the connections of the protective conductor, insulation resistance, RCD
triggering current, triggering time, etc., in accordance with local regulations.
Step 4 .
Verify that the connection cover is closed and secured with the fixing screws.
Step 1 .
Turn on the AC grid circuit breakers.
Step 2 .
Wait for the LED light to come on.
If the checks listed above were satisfactory, proceed as follows:
Before switching on the EV charger, check the effectiveness of the safety measure(s) of the system in
accordance with the local regulations.
Electrical systems or devices must be checked by professional and qualified personnel before
commissioning and switching on the unit.
9 Commissioning
Professional and qualified personnel must be experts in the field and are therefore responsible for
commissioning the system in accordance with the manufacturer’s instructions and local legislations.