IB70-8671
For more information visit: www.eaton.com
Instructional Booklet
Effective: July 2008
Page
9
O & M Manual for the EGS AutomaticTransfer Switch
with RTC-50 Control and Integral Loadcenter - 100 Amp
.
Figure 8. Cable Connection Locations (100 A).
Step 2:
The generator utility sensing connections are located on
the fuse block that is installed at the bottom of the power
panel. The utility sensing wires, required for proper gener-
ator operation, are connected at this point. See Section
4.7 for more detailed information on connecting the gen-
erator utility sensing wires.
Figure 9. Generator Utility Sensing Wires Connection.
Step 3:
Tighten all cables and wiring to specifications.
GEN LUGS
UTILITY
LUGS
GENERATOR
LOAD LUGS
UTILITY LUGS
LUGS
UTILITY SENSING WIRE CONNECTION
UTILITY
LUGS
LOAD
LUGS
GENERATOR
LUGS
GROUND
NEUTRAL