IB70-8671
For more information visit: www.eaton.com
Instructional Booklet
Effective: July 2008
Page
13
O & M Manual for the EGS AutomaticTransfer Switch
with RTC-50 Control and Integral Loadcenter - 100 Amp
SECTION 7: MAINTENANCE AND
COMPONENT REPLACEMENT
7.1 Introduction
In general, ATS equipment is designed to be relatively mainte-
nance free under normal usage. However, because of the variabil-
ity of application conditions and the importance placed on
dependable operation by this type of equipment, inspection and
maintenance checks should be made on a regularly scheduled
basis. Since equipment maintenance will consist mainly of keep-
ing the equipment clean, the frequency of maintenance will
depend, to a large extent, on the cleanliness of its surroundings.
If a significant amount of dust or foreign matter is present, a more
frequent maintenance schedule should be followed.
It is suggested that visual inspections of the equipment be made
on a regular basis, not just during regularly scheduled periods.
Always be alert for an accumulation of dirt in and around the
structure, loose parts and/or hardware, cracks and/or discolora-
tion to insulation, and damaged or discolored components.
Figure 12 is the wiring diagram for the EGS 100 Amp ATS switch.
Note:
Only qualified and experienced personnel should attempt any diag-
nostic work using this diagram.
Figure 12. Wiring Diagram for the EGS100L24R ATS (Shown Deenergized).
WARNING
HIGH VOLTAGES ARE PRESENT IN AND AROUND TRANSFER
SWITCH EQUIPMENT. BEFORE INSPECTING OR MAINTAINING THIS
EQUIPMENT, DISCONNECT THE LINE POWER FROM THE EQUIP-
MENT BEING SERVICED BY OPENING AND LOCKING OUT, IF POSSI-
BLE, THE NEXT HIGHEST DISCONNECT DEVICE. FAILURE TO
FOLLOW THIS PROCEDURE COULD CAUSE SEVERE PERSONAL
INJURY AND/OR DEATH.