11
|
Commissioning
Installer reference guide
216
ERGA04~08EA + 08S18+23EA
Daikin Altherma 3 R F
4P629093-1A – 2021.11
INFORMATION
When air purging in automatic mode, the first air purge is always for the main zone,
the second started air purge is always for the additional zone. To air purge the
domestic hot water tank circuit, choose [A.3.1.5.2]
Circuit
=
Tank
at the start of
the manual air purge of the main zone or additional zone.
To perform an automatic air purge
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to
Installer
—
2
Go to [A.3]:
Commissioning
>
Air purge
.
3
In the menu, set
Type
=
Automatic
.
4
Select
Start air purge
.
5
Select
OK
to confirm.
Result:
The air purge starts. It stops automatically when done.
6
To stop the air purge manually:
—
1
In the menu, go to
Stop air purge
.
2
Select
OK
to confirm.
11.4.3 Operation test run
Purpose
Perform test runs on the unit and monitor the leaving water and tank
temperatures to check if the unit is working correctly. The following test runs
should be made:
▪
Heating
▪
Cooling (if applicable)
▪
Tank
INFORMATION
The test run only applies to the additional temperature zone.
To perform an operation test run
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to
Installer
—
2
Go to [A.1]:
Commissioning
>
Operation test run
.
3
Select a test from the list.
Example:
Heating
.
Содержание EHVZ04S18EA6V