44
BLOWER OPERATING INSTRUCTIONS
14.
Figure 90. Open Ball Valve
A. FINAL INSPECTION
Before placing the blower into operation, always perform a final inspection
of all components used.
B. OBSERVER AT EXIT PIT
Station an observer with a 2-way communication device, at the far end of the Conduit,
where the Cable carrier will exit.
C. NOTIFY crew that preparations are complete and cable blowing is to begin.
IMPORTANT: It is recommended that if a reel-tensioning unit is not being used, the
cable reel should then be kept under control by a second operator who is required to
wear proper safety equipment and maintain a proper distance from the cable (See page
9).
D. OPERATION
1. Lower Tractor Drive Cover by pushing the clamp button (Figure 88).
2. Recall crash test push force & clamp force settings for installation.
3. Make sure Needle Valve for air block is closed (Figure 89).
4. Open air to machine (Figure 90).
Figure 88. Lower Tractor Drive
Figure 89. Needle Valve
Содержание Gulfstream 350e
Страница 1: ...Gulfstream 350e USER S GUIDE SAFETY MANUAL...
Страница 2: ......
Страница 3: ...3...
Страница 17: ...17 Figure 22 Insert USB Figure 23 Copy to USB...
Страница 19: ...19 Figure 26 WIFI On Figure 27 Select GS350 e Enter password Condux145 passwords are case sensitive f Connect...
Страница 50: ...50 Notes...
Страница 51: ...51 Notes...