41
L
6. Mount vertical steam distribution pipes.
• Remove protective plugs from the sockets of the collector pipe.
• Push vertical steam distribution pipes into the sockets of the collector pipe until they come to a
stop (the resistance of the O-rings inside the sockets must be overcome). Then, align nozzle
apertures to the air flow according to drawing below.
Note: To improve the gliding ability moisten the end of the vertical steam pipes and the O-rings
inside the collector sockets with water (do not use oil or grease!).
• Screw the M5x6 grub screws (allen key 2.5 mm) provided into the sockets (as shown below),
until they touch the vertical steam distribution pipes.
• Vertical steam distribution pipes with a length >1400 mm must be fixed to the duct ceiling us
-
ing the brackets supplied. Before tightening the brackets vertically align steam pipes using a
spirit level.
L> 1400 mm
Air flow direction
<200 mm
<200 mm
Air flow direction
>200 m
>200 mm
Содержание Esco
Страница 1: ...INSTALLATION INSTRUCTIONS Steam humidification system 1117775 EN 1310 Condair Esco L...
Страница 2: ......
Страница 14: ...14 5 Seal the bores inside the duct with silicone free sealant...
Страница 24: ...24 5 Seal the bores inside the duct with silicone free sealant...
Страница 40: ...40 5 Seal the bores inside the duct with silicone free sealant...
Страница 50: ...Notes...
Страница 51: ...Condair Ltd Printed in Switzerland Technical modifications reserved...