7. With the purlin in position, tighten the pipe strap at the
peak and secure the purlin in the pipe strap using a Tek
screw.
FRAME ASSEMBLY (CONTINUED)
8. Align the pre-marked location on the purlin with the
center of the inside rafter to achieve the proper rafter
spacing and tighten the cross-connector (#102546).
NOTE:
If needed, use a hammer to tap the cross-
connector and the purlin to center it between the
brackets that secure the struts.
9. After tightening the cross-connector, install a Tek screw
(FA4482) through the cross-connector and into the
purlin.
Position the Tek screw so that it also secures the
joint of the purlin pipes
.
Tek Screw
The first purlin and the first two rafters should appear
as shown:
10. Move down the rafters to the first rafter joint and place
a cross-connector over the inside rafter at that joint.
11. Select the first two sections of the second pre-marked
purlin and install it as you did the top/center purlin.
12. Position the cross-connector and the purlin over the
pipe joint of the rafter assembly and align the mark on
the purlin with the center of the rafter.
Remember:
To prevent damage to the main cover and
end panels, do not allow the purlin to extend beyond
the edge of the end rafter.
Tek Screw
End Rafter