7
CLEARSPAN
™
POLY BUILDINGS
Revision date: 05.20.20
End Rafter
Purlin
Awning
Hand Crank:
Roll-Up Side
Front of Shelter
(awning side)
Ground Level
36'
outside-to-outside
Cover, roll-up curtain and end panels are not shown.
Frame length of your building may differ from what is shown.
Mid Rafter
Cable Assembly
ClearSpan
™
Beef Master™ System
OVERVIEW
This section describes assembling your building. For
details of each assembly procedure, consult the Quick Start
Guide and the individual sections of these instructions. See
illustration below to identify main parts of shelter.
1. Grade, level, and layout the site, and identify the
required parts for each assembly procedure.
2. Dig post holes and set posts.
3. Assemble the main frame and install cables.
4. Assemble awning framing.
5. Install roll-up curtain.
6. Prepare and install the main cover (or covers).
7. Install end panels and doors.
ATTENTION:
This instruction manual describes the
assembly of the main frame and the installation of end
panels and main cover. The construction of the interior
tongue-and-groove walls and all other components
regarding the interior of the building can be completed
anytime after setting of the support posts and concrete
work is finished.
To help plan the construction, consult the diagrams near
the back of this manual to review all information before you
begin.
Consider time, weather, location, and the availability of
assistants, materials, and equipment when planning the
different phases of the construction. Based on these and
other factors, your sequence of constructing the different
components may differ from what is shown in the diagrams
throughout this manual.