CLEARSPAN
™
POLY BUILDINGS
10
Revision date: 05.20.20
2
Ground Level
6" x 6" x 9'-6"
6" x 6" x 9'-6"
6X6HB
6X6HB
SETTING THE POSTS
Set each corner post. Remember to drive the rebar
into the pre-drilled holes of the posts if this has not
been completed.
Verify that the distance between the corner posts is
equal and secure the posts in the holes by adding
backfill and tamping in place.
Consult an engineer to
determine the best material to use for backfill based
on the soil conditions. Check the diagrams in the
Quick Start section for spacing and required height.
Repeat the steps to prepare and set all remaining
support posts. Consult diagrams as needed.
After setting the posts, attach the post headers
between the support posts along the awning side
using 6X6HB header brackets. See the Connection
Details diagram (View 10) and diagrams below for
6X6HB Bracket
Install FAS13B
(#10 x 2-1/2")
here
Install FAJ117B
(5/16" x 3") here
18’
Diameter
6” x 6” Post
Backfill
w/Granular Material
Concrete Footing
Ground Level
6”
4’ Min.
rebar
fastener identification and locations.
Continue by attaching the rafter feet to the tops of the side posts.