Installation Guide for FibeAir IP-20S, FibeAir IP-20S Assured
Page 96 of 105
Ceragon Proprietary and Confidential
9.1
Site Acceptance Procedure
The purpose of the following procedures is to verify that all installation
requirements were noted and checked. Following this procedure will ensure
proper, long-lasting, and safe operation of the product.
The checklist below summarizes the installation requirements of the site.
SITE ACCEPTANCE CHECKLIST
1. SITE INFORMATION
Customer:
Radio model:
Site name:
Site code:
Radio link code:
Site address:
2. ANTENNA MOUNTING
Antenna mount type:
Mount is of sufficient height to clear local obstructions
OK
Mount is safely positioned to not cause a safety hazard
OK
Mount is secure and perpendicular
OK
Mount is grounded as per site specifications
OK
All steelwork is Galvanized or Stainless Steel as appropriate
OK
3. ANTENNA
Antenna type (model and size):
Antenna is securely fixed to mount
OK
Antenna is grounded as per site specifications
OK
Antenna sway braces are installed correctly (where applicable)
OK
Antenna Radome is securely fitted (where applicable)
OK
Water drain plugs are fitted and removed, as appropriate
OK
Antenna sealing O-Ring is properly fitted and not damaged
OK
Antenna/Launch unit polarization is as per link requirements
OK