Appendix B: Acceptance & Commissioning Procedures
This chapter provides Ceragon's recommended Acceptance and Commissioning
Procedure for IP-20. Acceptance and commissioning should be performed after
initial setup is complete.
The purpose of this procedure is to verify correct installation and operation of the
installed link and the interoperability with customer end equipment.
Ceragon's Acceptance and Commissioning procedure includes the following
stages:
•
Site Acceptance Procedure
•
Commissioning of Radio Link
The Site Acceptance Procedure is a checklist that summarizes the installation
requirements of the site at which the products were installed.
The commissioning tests cover the required configuration information that should
be recorded, and the tests that should be performed on the radio link.