10.1 Check list
DATA
Date
Performed by
Site
System serial number
Module serial numbers
Inview Serial number
ACTION
OK/ N.OK
Unplug all converters except one converter per phase (Just pull off the converter from the shelf, to interrupt
electrical contacts)
Check the commercial AC before closing the AC input breaker.
Switch ON the commercial AC
Check if converters are working (Green led)
Check the DC power supply and switch ON the DC breakers
Plug in all converters one by one
Check output voltage (on bulk output or on breaker)
Check if converters are working properly
Check if system has no alarm (Disable the alarm if any)
Read configuration file and review all parameters. Some parameters must be adapted according to the site
(LVD, load on AC, AC threshold level)
Switch OFF ACin and check if system is working on DC
Switch ON ACin and check if system correctly transferred load on AC
Switch OFF system and start on AC only
Switch OFF system and start on DC only
Check if display working properly (Inview)
Check if TCPIP working properly (if this option is present)
Test on load (if available)
ALARM
Switch ON AC input and DC input and check that no alarm are present
Pull out one converter and check alarm according to redundancy
Pull out two converters and check alarm according to redundancy
Switch OFF AC input (commercial power failure) and check the alarm according to the configuration
Switch OFF DC input (DC power failure) and check that the alarm according to the configuration
Check the different digital input according to the configuration (when used)
46
– Sierra 10 - 48/120 VAC – User Manual – v1.1
Commissioning