5.4
Initial commissioning
After installation has been completed, proceed as follows for commissioning of the
BEKOKAT
®
:
1st
Ensure that the pipework system is free of contamination and impurities.
2nd
Inspect the compliance with the safety instructions relating to the quality of the
compressed air. Refer to the "Assembly” chapter.
3rd
Inspect the compliance with the safety instructions for the electrical connections and
the voltage supply. Refer to the "Installation” chapter.
4th
Check if an EMERGENCY STOP switch / EMERGENCY STOP device is installed.
5th
Connect the alarm contacts for minimum and maximum temperature.
6th
Turn on the main switch.
7th
Connect the signal line for the bypass valve (option).
8th
Turn on the Start switch S0 / S1 "Converter Operation" to "ON".
The heating control light
BEKOKAT
®
lights up white (H4), the converter is heated up.
As long as the temperature of +150°C has not yet been reached, the valves remain
closed.
9th
The heating phase lasts about 5 hours.
After this, the valves open.
The heating up time of the
BEKOMAT
®
depends on the following factors:
Voltage
Ambient temperature
Air movement at the place of installation
Duration of shutdown of the assembly unit.
The specified value for the heating time can thus be exceeded or fallen below.