6 Commissioning
6.1 Basic information
Before the device is started up, it must be gradually adapted to room temperature!
6.2 Switching on the device for the first time
6.2.1 General information before switching on the device
Checklist
Before the device is started up for the first time, the following points must be checked:
•
Have the installation instructions been observed as described in
"Installation and wiring" on page 142
?
•
Have the permissible ambient conditions and environmental conditions for the device been taken into ac-
count?
•
Is the power supply connected correctly and have the values been checked?
•
Is the ground cable correctly connected to the ground connection?
•
Before installing additional hardware, the device must have been started up.
Caution!
Before the device is started up, it must be gradually adapted to room temperature! Exposure to direct
heat radiation is not permitted.
When transporting at low temperatures or in the event of large temperature fluctuations, the collection
of moisture in or on the device is not permitted.
Moisture can cause short circuits in electrical circuits and damage the device.
Requirements
The following criteria must be met before switching on the device for the first time:
•
The protective film has been removed from the panel.
•
The functional ground connections are as short as possible and connected to the central grounding point
using the largest possible wire cross section.
•
All connection cables are connected correctly.
•
A USB keyboard and USB mouse are connected (optional).
•
An Automation PC or Panel PC is connected (via DVI, SDL, SDL3 or SDL4).
6.2.2 Switching on the Automation Panel
Procedure
1. Connect the power supply and switch it on.
2. The device is operating.