5.5.9 Installing the IP54 VESA mounting unit
The following requirements must be met:
•
All connected cables must be disconnected.
•
The Automation Panel is no longer be installed on the VESA bracket.
1. Disconnect the power supply cable to the Automation Panel (disconnect the power cable). Disconnect from
all sources and poles!
2. Carry out electrostatic discharge at the ground connection.
3. Place the mounting unit frame on the panel. The openings in the frame must be lined up with the mounting
pins on the panel.
4. Install the frame on the panel using the 8 provided Torx screws (T25: 8x M5x20).
The tightening torque for each is 2.5 Nm.
5. Secure the cable grommets with the flat side facing upwards.
Notice!
It is important to note that the cables must first be inserted into the grommets before they are
pushed into the guide.
Failure to follow this instruction can result in damage to property.
6. If the mounting unit is used in conjunction with a PPC2200, the heat pipe including heat pipe cover must also