Load Cell Cable Wiring
At this point all of the load cell cables can be pulled through the installed conduit. As
an option and at an additional cost, digital load cell cables can be requested to be pre-
wired at the factory when ordering the scale.
Depending on your particular type of Centurion, find the correct wiring diagram on the
following pages. Additionally, a wiring diagram was included with your “scale package”
along with the foundation drawing.
It is important that all cables be installed so that they do not touch the ground and are
internal to the scale. Round cable hangers are attached to each module to enable you
to use zip ties to secure excess cable, by being bundled and attached to the hangers.