Prior to commissioning and before each use the machine must undergo the visual
and functional checks given below.
The instructions given below must be followed.
VISUAL CHECK
CHECK OPERATION
•
Visually check under and around the
machine to make sure that there are no
oil or fuel leaks.
•
Make sure that there is no hydraulic oil
leaking from the hoses and from the
other
components
(cylinders,
distributors, fittings, etc.).
•
Check that there are no cut or worn
electrical
cables
and
that
the
connectors are correctly secured.
•
Check the fuel level before starting so
as to prevent interruptions while
working.
•
Check the engine oil level.
•
Check the hydraulic oil level.
•
Make sure that none of the screws,
bolts or ferrules are loose or missing.
•
Make sure that all the "Seeger" safety
rings are present and correctly in place
with there washers.
•
Make sure that all the pins are in place
and correctly secured.
•
Make sure the tracks are not cut or
abnormally worn
•
Always check to make sure that track
tension is correct
•
Check, and if necessary grease, the
scissor runners, both those in contact
with the platform and those in contact
with the lower frame.
•
Check that the manual, the plates and
the stickers are on the machine.
•
Check that the steel structure is not
deformed.
•
Make sure there are no cracks in the
welds, damage or abnormal wear
•
Make sure that the 12V internal
combustion engine ignition battery is
•
With
the
platform
in
the
transport
configuration, place the machine with the
frame tilted with respect to the horizontal by a
value greater than 0.5° on the lateral. Operate
the platform lifting control, make sure that the
system automatically brings the frame to the
horizontal position
•
With
the
platform
in
the
transport
configuration, place the machine with the
frame tilted with respect to the horizontal by a
value greater than 0.5° on the longitudinal.
Operate the platform lifting control, make sure
that the system automatically brings the frame
to the horizontal position
•
With
the
platform
in
the
transport
configuration, place the machine with the
frame tilted with respect to the horizontal at
the maximum angle both on the longitudinal
and on the lateral. Operate the platform lifting
control,
make
sure
that
the
system
automatically brings the frame to the
horizontal position
•
Lift the platform without a load to the
maximum height and then lower it a few times;
make sure that the machine works correctly
•
Check the operation of the anti-shearing
device; this test is performed by lifting the
platform to a height that involves an angle of
the scissor frames greater than 12° with
respect to the horizontal and make sure that
the descent movement stops automatically at a
scissor angle between 7° and 9° (the vertical
distance between the ends of the scissors must
be greater than 50mm). Further movements
downwards are possible only after a 3s delay at
reduced speed.
•
Check the operation of the travel function with
the platform lifted; this test is performed by
Содержание 1090 EVO
Страница 7: ...7...
Страница 10: ...10 Maximum transport height allowed manual levelling and the adjustment of the travel speed is allowed...
Страница 22: ...22...
Страница 23: ...23...
Страница 49: ...49 37 Combustion engine 38 Fuel tank 39 Bi levelling chassis 37 38...
Страница 78: ...78...
Страница 80: ...80...
Страница 122: ...122 In this configuration the oil level must be as shown in the figure below A 60mm...
Страница 144: ...144...
Страница 145: ...145...
Страница 146: ...146...
Страница 147: ...147...
Страница 148: ...148...
Страница 149: ...149...
Страница 150: ...150...
Страница 151: ...151...
Страница 152: ...152...
Страница 156: ...156 6 Using the nut supplied point A 7 Move the front wheel back by pressing on the track with your foot...
Страница 161: ...161 8 ATTACHMENTS 8 1 Declaration of conformity...
Страница 163: ...163 MANDATORY ROUTINE INSPECTIONS Date Observations Seal Signature...
Страница 177: ...177 8 4 Hydraulic diagram See attachment 8 5 Wiring diagram See attachment...