A.07.370e - Edition 2.0
Installation
1. Remove the screws (A).
2. Remove the protection plate (B).
3. Strip the cables at the end.
In the case of a screened cable,
remove the outer sheet of the cable between the terminals
and the earthing bar.
4. Connect the two cables for each series circuit to the
corresponding output terminals (C).
5. Connect the cables to the earthing bars (D).
Use earthing
clamps.
- Screened cable: connect the screen to the earthing bar;
- Unscreened cable (E): connect the cable to the earthing bar for stress relief.
6. Install the protection plate and the screws.
6.13 Connect remote control cables
6.13.1 Connect multiwire or J-Bus (option)
Disassemble the connector
1. Remove the screws (A).
2. Note the correct side for each terminal block (B).
3. Remove the terminal blocks (B).
Note
For the connection scheme, refer to the label in
front of the output terminals.
E
C
D
B
A
Note
If the terminal blocks are not located on the correct sides, the remote control does
not work.
A
A
B
Содержание CRE 10
Страница 1: ...A 07 370e Edition 2 0 Installation Manual Constant Current Regulator Type CRE ...
Страница 14: ...14 A 07 370e Edition 2 0 Safety ...
Страница 44: ...44 A 07 370e Edition 2 0 Inspection and transport ...
Страница 64: ...64 A 07 370e Edition 2 0 Installation ...
Страница 85: ...A 07 370e Edition 2 0 85 Technical data ...
Страница 86: ...adbsafegate com ...