ZXC10-BTS (V5.4) Installation Manual
10-2
The installation method and procedure differs. In the precondition of quality, the
Installation Supervisor should install the antenna as per the actual situation flexibly and
reasonably by following the BTS engineering design documents and the installation
instructions of the special antenna provided by the manufacturer.
Prior to the installation of the antenna feeder system, inspect the qualification of the
installation staff to work at heights, check and prepare the installation environment, the
installation measures, the installation tools and the antenna feeder to be installed so that
the installation can be carried out successfully.
10.1.1 Preparations for Installation Staff
Generally, the installation of antenna feeder system is supervised by the Installation
Supervisor and carried out by the installation staff.
Requirements for the Installation Supervisor: He should be familiar with the materials,
tools and operation methods used in the antenna feeder installation, and be responsible
for organizing the installation staff and assigning proper tasks (especially working on
the tower) to the staff in the principle of "Safety First". The Installation Supervisor
should fill in the engineering data faithfully.
Requirements for the installation staff: Staff that can conduct the installation
professionally under the instruction of the supervisor. The staff working at heights
should have no acrophobia and be in good health. In addition, he should have the
qualification and certificate for working at heights, observe the requirements for using
the safety tools, have purchased life insurance policy, and should not drink.
10.1.2 Installation Environment Inspection
The environment inspection focuses on the following: The outdoor lightning protection
grounding cable should be in place with the core diameter more than 50mm
2
. The
distance between the antenna lightning arrester, the lightning protection grounding
point, the outdoor cabling rack, and the antenna embracing pole should meet the design
requirement. The strength and the wind-withstanding capability of the embracing pole
should also meet the design requirements. Check the preparation of the compulsory
tools and engineering auxiliary materials. Both parties should negotiate and define the
specific routing of the main feeder.