Page 4 of 28
801314UK - G4 Boiling chilled commercial installation instructions - June 2016 - V2.04
Before installation
•
Read the instructions and check if there is adequate space to install all of the components.
•
Note
Not all fittings are supplied with the appliance kit. Isolation valves are not supplied.
•
Check the mains water pressure is within min / max requirements (see page 9).
•
Check the water quality to determine if extra filtration will be required.
•
Note
This product must be fitted to a potable water supply.
•
Check the Command-Centre
TM
rating plate and ensure correct power is available.
•
Check the under counter cupboard floor supporting the Command-Centre
TM
is adequate for its
total weight, when full of water.
Before commissioning
•
Check the system has been installed correctly.
•
Check all plumbing fittings have been tightened.
•
Ensure the outlet and vent pipes are positioned to drain correctly.
•
Ensure there is adequate ventilation.
•
Check all tubes and pipes from the Command-Centre
TM
to the tap have a constant rise and there
are no sags or kinks in the hoses.
•
Check all electrical connections are correct and there are no loose wires.
Commission
(see section 5)
•
Flush the supply line before connecting.
•
Turn on the water and check for leaks.
•
Flush the filter(s).
•
Activate / enable the booster (if fitted).
•
Calibrate the safety sensor for boiling models.
•
Where applicable, programme the Command-Centre
TM
to suit the customer’s requirements.
Installation checklist