12
AYK550-UH User’s Manual
Installation
Wiring IP 21 / UL Type 1 Enclosure (Base Drive)
1. Open the appropriate knockouts in the
conduit box. (See "Conduit Kit" above.)
2. Install thin-wall conduit clamps (not supplied).
3. Install conduit box.
4. Connect conduit runs for input power, motor
and control cables to the box.
5. Route input power and motor wiring through
separate conduits.
6. Strip wires.
7. Connect power, motor, and ground wires to
the drive terminals. See "Wiring Overview" on
page 9.
8. Route the control cables through the conduit
(not the same conduit as either input power or
motor wiring).
9. Strip the control cable sheathing and twist the
copper screen into a pig-tail.
10. Connect the ground screen pig-tail for digital
and analog I/O cables at X1-1. (Ground only
at drive end.)
11. Connect the ground screen pig-tail for RS485
cables at X1-28 or X1-32. (Ground only at
drive end.)
12. Strip and connect the individual control wires
to the drive terminals. See "Wiring Overview"
on page 9.
13. Install the conduit box cover (1 screw).
2
X0007
3
X0005
4
IP2004
7
7
5
10
8
IP2005
12
Summary of Contents for AYK 550
Page 256: ...D1 AYK550 UH User s Manual Appendix D Appendix D Base Drive Drawing 205662 Drawings Fig 1...
Page 257: ...AYK550 UH User s Manual D2 Appendix D Base Drive w Fused Disconnect Drawing 205648 Fig 2...
Page 258: ...D3 AYK550 UH User s Manual Appendix D Base Drive w Non Fused Disconnect Drawing 205647 Fig 3...