4 Putting into operation
1. Move vehicle
Y
close to machine
X
so that the length of the battery
jumper cables is sufficient.
2. Stop the engine of vehicle
Y
.
3. Engine covers of both vehicles are open.
4. Remove the red cover
E
.
5. Connect the battery jumper cables in the following order:
A – B – C –
D
.
6. Start the engine of vehicle
Y
.
7. Wait five minutes for the empty battery to be charged a little.
8. Start the engine of machine
X
.
9. Switch on the boom light of vehicle
X
in order to avoid voltage peaks
and to protect the electronic system.
10.Disconnect the battery jumper cables in the following sequence:
D – C
– B – A
.
Fig. 117
B
C
_
+
A
D
Designations/symbols
Meaning
X
Machine with empty battery
Y
Vehicle with full battery
A
Positive/vehicle
X
B
Positive/vehicle
Y
C
Negative/vehicle
Y
D
Negative/vehicle
X
Full battery
Dead battery
Fig. 118
A
E
Fig. 119
D
Summary of Contents for ET35
Page 14: ...1 8 BA E16 en 1 0 E16_10_100 fm 1 Foreword Notes...
Page 46: ...3 8 BA E16 en 1 0 E16_10_300 fm 3 Introduction Warning labels Fig 9 symbolic representation...
Page 64: ...3 26 BA E16 en 1 0 E16_10_300 fm 3 Introduction Notes...
Page 194: ...6 8 BA E16 en 1 0 E16_10_600 fm 6 Transportation Notes...
Page 252: ...8 8 BA E16 en 1 0 E16_10_800 fm 8 Malfunctions Notes...
Page 292: ...9 40 BA E16 en 1 0 E16_10_900 fm 9 Technical data 9 15 Dimensions ET35 symbolic representation...
Page 294: ...9 42 BA E16 en 1 0 E16_10_900 fm 9 Technical data EZ36 symbolic representation...
Page 296: ...9 44 BA E16 en 1 0 E16_10_900 fm 9 Technical data Notes...
Page 300: ...S 4 BA E16 en 1 0 E16_10_3SIX fm...