Chapter 5, Operating Instructions: Single Point Operation
E.H. Wachs
Part No. 81-MAN-00, Rev. 0-0610
71
Setting Up and Mounting the EP 424
You will probably find it easiest to assemble the main com-
ponents of the EP 424 as you install the machine. The fol-
lowing is the recommended sequence for installation:
•
Configure and mount the mandrel in the workpiece, as
described in the previous section.
•
Install the machine body onto the mandrel.
•
Install the tool holder and tooling in the single-point
slide.
•
Install the drive motor.
If desired, you can assemble the machine and then mount it
on the workpiece. You will need a lifting device to support
the machine as you mount it.
Assembling the Machine Components
The following procedure assumes that the mandrel has been
mounted in the pipe, as described earlier in this chapter.
It is recommended that you
using a lifting device to pick
up the EP 424. If you are lift-
ing it manually, have two
operators lift it.
1.
Attach a crane or other lifting device to the lift hook
on the machine body.
Figure 5-62. Attach the lifting device to the lift ring.
2.
Use the lifting device to pick up the EP 424 and posi-
tion it for mounting on the mandrel. If you do not have
a lifting device, two people can lift the machine into
place using the handles.
NOTE
Summary of Contents for EP 424
Page 2: ...EP 424 End Prep Machine Part No 81 MAN 00 Rev 0 0610 E H Wachs...
Page 8: ...EP 424 End Prep Machine 4 Part No 81 MAN 00 Rev 0 0610 E H Wachs...
Page 14: ...EP 424 End Prep Machine 10 Part No 81 MAN 00 Rev 0 0610 E H Wachs...
Page 92: ...EP 424 End Prep Machine 88 Part No 81 MAN 00 Rev 0 0610 E H Wachs...
Page 98: ...EP 424 End Prep Machine 94 Part No 81 MAN 00 Rev 0 0610 E H Wachs...
Page 100: ...EP 424 End Prep Machine 96 Part No 81 MAN 00 Rev 0 0610 E H Wachs...