29
5773 597 - 04
Vitocrossal 200, CM2 400, 500 and 620 Installation
Boiler
Gas Flue Adaptor
1. Fully insert flue gas adapter inside the flue outlet
(if used with stainless steel piping).
Note:
Connect the flue outlet with the flue pipe
via the shortest possible run, with slight rise
(min
3
o
). Avoid sharp bends.
2. Connect flue system. Size: 10 in. (250 mm).
Note:
Support all venting components; make all
connections free of load and torque stresses.
The venting system must be securely
supported by an anchoring system as outlined
by the venting manufacturer.
IMPORTANT
The boiler flue gas collector vent is not designed to
support the weight of the venting system.
Control Panel and Covers
1. Plug in control interface cable and install cover.
2. Install control cosmetic cover.
3. Install buffer panel to the top rail and secure with
4.8 mm metal screws.
Legend
A
Control interface with cover
B
Buffer panel
C
Cosmetic cover
Note:
The flue gas adaptor is not included with the boiler
and if required must be supplied by the venting
manufacturer.