5: Maintenance
5-2
UPS338-01-00 PowerWAVE 8000-RI DPA User Manual Dated 5 April 2013
5.5
Battery Testing
The battery test takes approximately 3 minutes and should be performed only if:
• There are no alarm conditions
• The battery is fully charged
• The input mains supply is present
Battery testing can be carried out independently of the operating mode (Off-line or On-line) and whether or
not the load is connected.
The battery test procedure can be performed from the UPS front panel (See paragraph 4.3.5).
5.6
Battery Maintenance
The battery maintenance shall be done by an authorized Uninterruptible Power Supplies Ltd Service Partner.
5.7
Battery Disposal and Recycling
Batteries contain dangerous substances that will harm the environment if thrown away. If you change the
batteries yourself, call qualified organizations for battery disposal and recycling.
Summary of Contents for PowerWAVE 8000DPA RI
Page 1: ...User Manual PowerWAVE 8000DPA RI Pioneering solutions for total power protection ...
Page 2: ...UPS338 01 00 PowerWAVE 8000 RI DPA User Manual Dated 5 April 2013 ...
Page 4: ...UPS338 01 00 PowerWAVE 8000 RI DPA User Manual Dated 5 April 2013 ...
Page 8: ... iv UPS338 01 00 PowerWAVE 8000 RI DPA User Manual Dated 5 April 2013 ...
Page 10: ...1 Safety 1 2 UPS338 01 00 PowerWAVE 8000 RI DPA User Manual Dated 5 April 2013 ...
Page 16: ...2 General Description 2 6 UPS338 01 00 PowerWAVE 8000 RI DPA User Manual Dated 5 April 2013 ...
Page 42: ...3 Installation 3 26 UPS338 01 00 PowerWAVE 8000 RI DPA User Manual Dated 5 April 2013 ...