OUTLINE OF INSTALLATION WORK
Items marked with a box are jobs which you should do. Use the list given below as a check list.
1. Preparations for Introducing the Machine
Complete the following preparations:
Building construction and floor work (Irregularity in the floor levelness: 5 mm or less, Surface irregularities of the
floor where the legs of the machine are to be positioned: 1 mm or less)
Foundation work, floor marking, and anchor bolt laying work*
(* This job is not required if you select the gluing installation method.)
Power wiring (to the installation position of machines) and installation of circuit breakers on the switchboard
Pneumatic piping (to the installation position of machines)
Installation of air compressor(s)
Air-conditioning work
2. Preparations for Installation
Complete the following preparations:
Arrangement of workers
Setting-up of forklift, hand lifts, and small jacks
Procurement of Polymortar (for bolting installation) and Araldite or Sikadur (for gluing installation)
Customs clearance for machines
Receiving and carrying machines to your factory
Installation can be started at this stage.
Toyoda service personnel can be
dispatched at this stage.
3-1. Installation of Weaving Machines and Related
Facilities
Complete the following preparations under the on-site
supervision of Toyoda service personnel:
Unpacking and installation of machines
Leveling of machines
Installation of EDP stand(s)
Installation of cheese stand(s)
Power wiring to machines
(main power and inverter power)
Pneumatic piping to machines
3-2. Preparations for Weaving Start-up
Complete the following preparations:
Warp yarn preparation
Procurement of weft yarn, leno yarn,
waste-selvage yarn, and additional yarn
Installation of winder for weft cheeses
Installation of leno yarn winder
Installation of waste-selvage yarn winder
Procurement of oil and grease
Adjustment and Trial Run
Weaving Start-up
Start of Production