Commissioning – Check Connections
EI Residential Solar Solution Installation Manual |
30
Commissioning
Commissioning must be performed by a licensed electrician or other qualified person in
accordance with local, national, and regional code requirements.
To commission the system, you will:
•
Check Connections
•
Power On the System
•
Run the Tigo Energy Intelligence App
Check Connections
Before powering on the system, double-check:
•
Inverter–link connections:
o
CT
o
COMM
o
EPS (INV)
o
GRID (INV)
•
AC/DC connections to breaker panels.
•
Battery power and COM cables.
•
Earthing cables and connections.
•
Conduit attachments are sealed and bonded where necessary.
•
Unused conduit openings are fitted with waterproof caps (provided) or were left
unopened.
•
The battery power switch and all other power sources connecting to the system are OFF.
Power On the System
Ensure grid voltage is within 220/240V.
To power on the system for the first time:
1.
Turn on the DC breaker located on the side of the BMS.
2.
Press the BMS power button to start the battery.