Applications Guide
143
Measurement of a grounded two-bushing energy storage capacitor with additional resonating
inductor, connected for C
1
determination.
Test Connections
DUT
High Voltage
to
INPUT A
to
HV GND
to
Test Mode
C
1
2
1
Tank GND
UST A
C
G1
2
1
Tank GND
GST gA+B
C
G2
2
1
Tank GND
GST gA+B
C
G1
+ C
G2
1 + 2
Tank
GND
UST A
Measuring Data Interpretation
When available the measurement results should be compared with the nameplate values or with
results obtained in previous measurements.
The power factor of the earth insulation is expected to be in the order of 0.5% or less. The main
capacitor should have a much lower power factor.
An increase in capacitance of several percent is an indication of short-circuited layers of the insulation
or the dielectric.
14.7
Circuit Breakers
For insulation measuring purposes high voltage circuit breakers can be classified into two groups.
Live tank breakers whose interrupting chamber is on HV potential and dead tank breakers whose
interrupter chamber is accommodated in an earthed metal housing.
The applied test voltage for breakers should not exceed 10% to 25% above their rated operating line-
to-ground voltage. That means in formula:
Summary of Contents for MIDAS 2881
Page 6: ......
Page 10: ......
Page 64: ...54 Software...
Page 109: ...Accessories and Options 99 Schematics Overview of the 5289 inductor and it s shielding...
Page 119: ...Conformity 109 13 Conformity...
Page 120: ...110 Appendix Appendix...
Page 159: ...Applications Guide 149...