Planning, Installation, Maintenance and Operating Instructions
dw
62-2 ME Sliding Doors
- 7 -
Assembly of the angle and ceiling brackets
-
Check height over the entire width (observe unevenness of the floor!)
-
For wall mounting
Measure the height for the angle brackets from the highest point of the floor (for rough concrete from the
metre level). It is essential to observe the minimum dimension “D” (see table above) from the lower edge of
the lintel to the bracket bore holes. Mark further divisions using a tube level or surveyor’s level.
-
For ceiling mounting
Measure the distance from the lower edge of the ceiling to the highest point of the floor. Subsequently fix the
ceiling mounting bracket to the lowest point. Mark further divisions using a tube level or surveyor’s level.
Position the ceiling mounting brackets with flat steel for metal casing attachment (see 9) at equal distances.
Fixing the upper wall seals
For wall mounting
Fix all the wall brackets together
with the upper wall seal,
since one side of this wall seal
is jammed between the lintel
and the angle bracket
For ceiling mounting
Using FAZ 12/10 stay bolts
Drill bit:
Ø
12mm
Drilling depth: Min.
Ø
95mm
For brackets set in concrete
Weld the wall seal to the
bracket plates.
Welding (s): a
≥
4, l
≥
30mm
7.2 Fixing the Lateral Wall Seals and the Weight Box:
Tlg. 600
£
Tlg. 300
£
Tlg. 450
£
4
4
4
3
1
2
2
Tlg. 450
£
4
Tlg. = division (div.)
-
Bolt on the weight box (1)
-
Fix the run-in bracket (2) to the weight box
using steel blind rivets
∅
4x8mm or plug welding.
-
Bolt on the lateral wall seal (3)
-
Fix the upper wall seal (4)
(see above)
See tables for fixing equipment (5)
Push the lateral wall seal up underneath the
upper wall seal. The lateral wall seal (3) has to be
fixed in place before hanging the last door leaf
otherwise it is covered and no longer accessible