T.Werk GmbH - CHRONOS Click Pitched roof solution - Assembly instruction     Page 4 of 24 

 

 
1   CHRONOS Click pitched roof solution 

 
The CHRONOS Click mounting system is used 
for  mounting  a  photovoltaic  system  on        
sloping roofs of all types (rafter/ purlin roof; 
roof  tiles/tiles,  plain  tile  roofing,  slate  tiles, 
trapezoidal  sheet  metal,  seam  roofing,   
sandwich  elements,  fibre  cement  panels). 
Depending on the roof, the roof is attached 
with hanger bolts, roof hooks and clamps. An 
adapter plate, pre-assembled with a CHRONOS attachment, enables a problem-free connec-
tion of the rail system. The great strength of the mounting system is the Click system. Clicking 
the 3.15 m and 5.15 m CHRONOS Click profiles into the CHRONOS adapters guarantees simple 
and  quick  installation.  The  modules  are  mounted  crosswise  or  upright  parallel  to  the  roof.  
Adapted to this, the system structure is single-layer or double-layer in cross-connection. The 
mounting system is supplemented by a project-specific wind suction calculation as proof of 
stability. 
 
 

2   Usage of the assembly instruction 
 

The 

installation instructions

 are part of the CHRONOS Click assembly system. The document 

contains important information on all phases of the product's life, especially on assembly. The 
assembly  instructions  are  intended  for  qualified  specialists  for  the  (dis)assembly  and           
maintenance of the CHRONOS Click assembly system. 

 
Qualified specialists

 are persons who, based on their technical training, knowledge and expe-

rience as well as their knowledge of the relevant standards, are able to assess the specified 
assembly steps and carry them out professionally as well as recognize possible hazards. 
 
 

3   General informations 

 

 

Keep the installation instructions for the entire lifetime of the product. 

 

Observe all country-specific regulations. 

 

Carry  out  the  installation  exclusively  according  to  the  project-specific  module  allocation 
plan of T.Werk GmbH. 

 

Coordinate all changes in the assembly of the mounting system as well as all changes to the 
building that take place after the project-specific module layout plan and the project-spe-
cific wind suction calculation have been created with T.Werk GmbH. Otherwise, the war-
ranty and the proof of stability shall expire. The same applies to incorrect information pro-
vided when placing the order. 

 

 

 

Summary of Contents for CHRONOS Click

Page 1: ...CHRONOS Click Pitched roof Translation of the assembly instruction into english 49 8283 997904 0 info t werk eu www t werk eu...

Page 2: ...e 2 of 24 Manufacturer Contact ph 49 8283 997904 0 fax 49 8283 997904 299 e mail info t werk eu www t werk eu T Werk GmbH Zur Sch nhalde 10 D 89352 Ellzee CHRONOS Click Pitched roof Translation of the...

Page 3: ...itched roof solution 4 2 Usage of the assembly instruction 4 3 General informations 4 4 General safety instructions 5 5 Warranty conditions 6 6 Structure of the CHRONOS Click mounting system 7 7 Trans...

Page 4: ...ruction The installation instructions are part of the CHRONOS Click assembly system The document contains important information on all phases of the product s life especially on assembly The assembly...

Page 5: ...Only carry out the subsequent commissioning if you are a qualified specialist Only carry out maintenance and servicing if you are a trained specialist Failure to do so may result in personal injury a...

Page 6: ...ing improper maintenance instability and insufficient stability of the building substrate Signs of wear wearing parts Optical surface changes e g Discolouration of edges and punched holes on galvanize...

Page 7: ...roof hook ALU VAR triple adjustable roof hook pre assembled with CHRONOS roof adapter Bracket angle 35 mm EN AW 6082 T6 Base plate 120 mm EN AW 6063 T66 Screws SW13 A2 SOV01099 0 5 kg CHRONOS Dachhake...

Page 8: ...n ding on length Hanger bolt for wooden substructure M10 x 200 mm 3xFM 1xEPDM seal calotte SW7 stainless steel A2 building authority approval SOV00036 0 121 kg M10 x 250 mm 3xFM 1xEPDM seal calotte SW...

Page 9: ...00539 0 05 kg Round seam clamp Alu big SOV01050 0 05 kg RIB ROOF 465 clamp A2 SOV00225 0 4 kg RIB ROOF 500 clamp A2 SOV00838 0 4 kg RIB ROOF 500 clamp original SOV00957 0 4 kg Domitec clamp SOV00720 0...

Page 10: ...6063 T66 EN 755 9 Surface press finish w x h 44 8 x 50 mm SOV00849 2 98 kg Length 5 3 m Material Aluminium EN AW 6063 T66 EN 755 9 Surface press finish w x h 44 8 x 50 mm SOV00905 4 92 kg CHRONOS rai...

Page 11: ...H Depending on FH 0 014 kg bis 0 020 kg 7 Transport For the transport of the CHRONOS Click assembly system the CHRONOS Click profiles are packed into bundles according to the length of the profiles an...

Page 12: ...5 Torx TX 40 6 Angle grinder with diamond wheel 7 Safety eyewear 8 Open end spanner SW13 Requirements 1 First check the roof for damage cracks holes brittleness If necessary document the existing dama...

Page 13: ...le position 2 Profile position CHRONOS RC Specification for number and placement of roof hooks statics rafter spacing 65 120 cm Cantilever up to 500 mm depending on snow load With low snow loads and s...

Page 14: ...ow Distance depends on Module dimensions clamping range of the modules specifi cation of the module manufacturer Distance of the mod ules between the rows approx 10 mm near the roof hook 1st profile l...

Page 15: ...dwich elements the substructure is mainly laid horizontally wooden or steel purlins Therefore it is common to lay the modules horizontally with a single layer system Measure the profile position and t...

Page 16: ...s shafts Make sure that the EPDM seals which are already pre mounted on the hanger bolt are in full contact 2 5 Screw the hanger bolts vertically downwards Do not tighten the hanger bolt with torques...

Page 17: ...etween seams depending on snow load skip rebates clamp each rebate at the outermost two rebates Cantilever depending on snow load up to 250 mm Vertical distance of the 1st profile and number of clamps...

Page 18: ...Click Profile into place Use a lever tool to help you Place the lever tool on the CHRONOS Click Profile near a roof fastening point Place the lever tool in the channel as shown in the picture below Cl...

Page 19: ...profile at joints 4 5 Click the second profile into the rail con nector 1 Then slide the rail connector over both profiles 2 4 6 Screw two thin sheet metal screws into the holes provided in the rail c...

Page 20: ...y 2 Screw in the cylinder head screw M8 x 14 of the CHRONOS cross connector set with a hexagon socket SW6 at a torque of 10 Nm to fix the CHRONOS cross connector set on the first profile layer 3 5 3 A...

Page 21: ...at the beginning of the rail Make sure that there is a dis tance of 3 5 cm from the end of the profile 6 3 On the free standing side at the begin ning of the row place one compensat ing profile each...

Page 22: ...cket SW6 with a torque of approx 10 Nm observe the specifica tion of the module manufacturer 6 6 Repeat assembly steps 6 4 and 6 5 un til the end of the row 6 7 At the end of the row an additional com...

Page 23: ...Visually check that all modules are in the correct position 2 Spot check the strength of all screws 3 check the correct position of the balancing profile at the end of the row Contact T Werk GmbH if a...