OPERATION & MAINTENANCE MANUAL SWE215F
106
Breaking work
Note
Select matched model of breaker
according to excavator model.
Main applications of breaker
:
Rock crush
Road construction
Structure demolition
Keep the chisel pushed perpendicularly against
the impact surface when carrying out breaking
operation.
When applying impact, push chisel against the
impact surface and operate so that the chassis
rises approx. 50 mm (2 in) off the ground. Do
not let the machine come further off the ground
than this amount.
Always keep the chisel pressed against the
impact surface properly to prevent using the
impact force when there is no resistance.
Adjust bucket cylinder at all time, always keep
chisel pushed perpendicularly against the
impact surface.
When it’s difficult to break, do not apply
continuous impact to the same surface for
longer than 1 minute. Change the point of
impact and carry out breaking operation closer
to the edge.
Summary of Contents for SWE215F-5
Page 137: ...OPERATION MAINTENANCE MANUAL SWE215F 130 4 4 10 Hoses...
Page 170: ...OPERATION MAINTENANCE MANUAL SWE215F 163 5 TECHNICAL SPECIFICATION...
Page 174: ...OPERATION MAINTENANCE MANUAL SWE215F 167 5 1 4 SWE215F 5 Electrical Schematic...
Page 176: ...OPERATION MAINTENANCE MANUAL SWE215F 169 5 1 6 SWE215F 5 Hydraulic Schematic...
Page 178: ...OPERATION MAINTENANCE MANUAL SWE215F 171 6 NOTE FOR SAFETY...