Checklist for Completed Installation
1
Proper clearances for service access have
been maintained in front of the equipment.
2
Equipment is level and mounting fasteners
are tight.
3
Field installed piping completed.
4
All fi eld installed piping leak tested.
5
Condensate drain line connected.
6
Water supply line connected to humidifi er
(if applicable). If manual cut-off valve is
installed, open valve.
7
Humidifi er “On/Off/Drain” switch is in “On”
position.
8
Filter(s) installed.
9
Incoming line voltage matches equipment
nominal nameplated rating ± tolerances.
10
Main power wiring connections to the
equipment, including earth ground, have been
properly installed.
11
Customer supplied main power circuit breaker
(HACR type) or fuses have proper ratings for
equipment installed.
12
All wiring connections are tight.
13
Foreign materials have been removed from
inside and around all equipment installed
(shipping materials, construction materials,
tools, etc.).
14
Inspect all piping connections for leaks during
initial operation.