cyberair 3PrO cw2 Original instructiOns
5.2 Positioning the unit
You will need two mounting aids as shown below.
When placing the unit on a raised floor stand, this must be installed first. Refer to the instructions in the chap-
ter „Raised floor stand“.
WArnInG
risk of crushing limbs
A defective lifting device can lead to the uncontrolled fall of the A/C unit.
Do not stay under suspended loads! Wear safety boots.
Mounting aids
Pallet height
transport with a fork lift
• transport the A/C unit on the pallet as close
as possible to the installation site.
• keep at hand mounting aids at the left and
right unit side.
• lift the units of cabinet size 1-4 with one fork
lift, the units of cabinet size 5-7 with two fork
lifts by 50mm.
• remove the pallet.
• put the mounting aids at the left and right unit
side.
• drop the A/C unit.
• lift the support surface of the mounting aids
at a sufficient height so that the weight of the
A/C unit lies on the mounting aids. Secure the
mounting aids by belts around the unit.
• take away the fork lift from under the unit.
• drive the unit by the mounting aids to the
installation site.
• drop the unit, loosen the belts and pull away
the mounting aids.
A/C unit transport with mounting aids