11
S
Upon delivery, uncrate the Stryker Documentation Station, transport to the appropriate location, and
assemble the three sections:
1. Roll the base section into place.
2. Lift and level the base by adjusting the four leg levelers, found at each corner, with a screw
driver.
3. Lift the middle section and set it on top of the base.
4. Center the middle section over the base and then push the middle section back until it stops.
5. Use the 2" #10 fasteners provided by the manufacturer to screw the middle section to the base
section. Use the pre-drilled holes at the top of each of the four corners of the base section to at-
tach the two sections.
6. Repeat steps 2-5 to attach the top section to the middle section.
Note
OSPHD anchoring details available from project manager upon request.
5.1.2
Additional Documentation Station Notes
• The right side of the documentation station is the standard side for the Infinity router.
• Stryker provides the back boxes for all the outlets in the documentation station. All electrical
outlets and face plates must be provided and installed by the hospital/Contractor.
• Stryker does not engrave or label circuit IDs on faceplates.
• Use the duplex outlet, in the bottom left cabinet of the documentation station, for the Ethernet/
Comm connection plate. Stryker only supplies the metal back box for this outlet.
• The bottom section is on casters and will easily roll into place. This allows for the electrician to
easily run power to the documentation station before rolling into place.
• There will be a 1" gap between the base of the cabinet and the finished floor. Stryker recom-
mends coving/flashing up the floor for cleaning purposes.
• Once in place, Stryker recommends sealing or caulking the sides of the documentation station
to the wall.
• The top of the documentation station is a flat surface and Stryker does not provide a soffit.
• Stryker recommends one circuit to feed the top and middle outlets, one circuit to feed the Infin-
ity side of the cabinet, and one circuit for the Power Supply box side of the cabinet.