4. Party Responsibilities
The responsibilities associated with planning and preparation for installation of Operating Room
Information System equipment will be shared between the Hospital, Contractor, and Stryker. These
responsibilities are outlined below.
4.1 Hospital Responsibilities
1. Fill out the Ship and Installation Confirmation Form provided by the Stryker Representative.
This must be completed eight (8) weeks prior to the requested installation date.
2. The hospital must supply Stryker with up-to-date drawings in .dwg format (CAD) including but
not limited to:
• Room layout plans (current and proposed)
• Electrical services drawings
• Mechanical services drawings
• Elevation drawings
• Structural steel (support structure) drawings
• Ceiling drawings
3. The hospital must ensure Stryker is notified of all revisions and changes to drawings prior to and
during the scope of the project.
4. Accept delivery of Stryker equipment.
5. All Stryker-supplied equipment should be stored in a clean, temperature-controlled, dry envi-
ronment prior to installation. Failure to comply may result in damage to the equipment, failure
of life support components, damage, and theft.
6. On or before the installation start date, deliver Stryker crates and equipment to the proper
room(s).
7. Remove and dispose of the pallets, boxes, and trash during and after the installation.
8. On the final day of installation, sign Stryker Installation Acknowledgement Form. This form
must be signed before the room can be turned over to the hospital.
4.2 Contractor Responsibilities
1. Coordinate subcontractors.
2. Prior to the installation start date, provide all rough-in requirements as explained in this manual
and the Stryker rough-in drawings.
3. Prior to the installation start date, run all cabling, electrical, and data as instructed in this
manual and the Stryker Communications drawings.
4. Provide and pull all cables outside the operating room as specified in this manual.
5. Prior to the installation start date, connect all the required electrical circuits.
6. Prior to the installation start date, complete all work involving dust, paint, and flooring.
7. All non-Stryker equipment that is going to be connected to Stryker's ORIS equipment must be
installed prior to Stryker's installation start date.
8. All Stryker equipment that attaches to the building structure, such as Documentation Sta-
tions, Plasma/LCD display mounting brackets, and LCD projector mounting brackets, must be
mounted prior to Stryker's installation date. Exceptions are Stryker's booms and lights.
9. Prior to installation start date, any documentation station or cabinets that will house Stryker